CONTRACTOR: Foresite Concepts, Inc.
ESTIMATED SCHEDULE: Begins week of 7/10 and anticipated to take ~14 weeks (weather dependent).
Work will be conducted in the following phases:
Phase 1 (2 crews) – 3 weeks
17th Avenue Storm Drainage – Ex. Inlet 5, 10, 6, 9, 7 & 8.
Reed St Curbs & Patch Paving – between 16 Ave & 17 Ave.
Tree Clearing – 14th Street (Paper Street)
Phase 2 (2 crews) – 2 weeks
Reed St Storm Drainage – Between 15th Ave & 16th Ave.
Reed St Curbs & Patch Paving – between 15th Ave & 16th Ave.
Phase 3 (2 crews) – 3 weeks
Reed St Storm Drainage/Curbs – between 13th Ave & 14th Ave.
Reed St Curbs & Patch Paving – between 14 Ave & 15 Ave.
Phase 4 (2 crews) – 4 weeks
Storm Drainage - Paper Street Between Reed St & Sansome St.
Sanitary Sewer - Paper Street Between Reed St & Oak Street.
Phase 5 (1 crews) – 2 weeks
Patch repair balance of all trenches
Mill & Overlay all roads
MISCELLANEOUS:
Work Hours: 7 AM to 5 PM Monday through Friday only.
- Timing: Contractor will provide flyers to each block and time them approximately a week before work is scheduled to occur.
- Driveway Restrictions: concrete curbs are reduced to a 1” reveal at the driveways. The plan is to install all of the depressed curbs on the block at one time, then place a steel plate over them soon after they are poured, allowing use of the driveway on the day the curbs are poured. The time prohibiting the use of the driveway is under 1 working day.
- Project team (Township and Contractor) is committed to accommodating the local residents to this project.