-
Storm Ida Projects
-
Other Projects
<
>
Check back for updates - last updated June 8, 2023
The following is a list of Caln Township infrastructure projects intended to address damage caused or exacerbated by Storm Ida. Some of the projects are eligible for partial reimbursement by FEMA and the Township is working diligently to follow all FEMA regulations in order to maximize our reimbursements. As we work through the engineering and bid process for these projects, status updates will be provided. Where applicable, click on a project name to access a PDF of the engineer's design file for that project.
# |
Project Title |
Status |
1a |
Bridge construction underway - anticipated completion by August 2023. |
|
1b |
Municipal Drive Streambank and Pedestrian Walkway Repair |
Completed |
2 |
Completed |
|
3 |
Construction in progress. Project construction underway - anticipated completion by 4/28/2023. Bid awarded and project anticipated to begin within next 60 days (from 11/21), subject to weather and supply chain issues. Notice to affected residents will be issued prior to work starting. Survey has been completed. Currently developing plot plans in AutoCAD with design underway. |
|
4 |
East Fisherville Road Bridge Demolition* |
Completed |
5 |
Fisherville Road Streambank Stabilization (and road repair) |
Completed |
6 |
G.O. Carlson (Beaver Creek Crossing)* |
Bid documents being created. Survey has been completed. A preliminary analysis has been completed. Developing emergency permit for submission to PADEP. The emergency permit will allow the Township to clean the stream and culverts of debris to elminate flooding risk in the short-term. The intent is to obtain an emergency permit and perform the cleaning in April 2022/early May 2022. Design underway. |
7 |
Humpton, Lynn, Williams Culvert Repair* |
Bid documents being created. Survey has been completed. Currently developing plot plans in AutoCAD with design underway. |
8 |
Completed |
|
9 |
Completed |
|
10 |
Completed |
|
11 |
S. Lloyd Ave. Streambank Stabilization (and culvert repair) |
Completed |
*Project is not eligible for FEMA reimbursement |
# |
Project |
Status |
1 |
2022 Road Paving Project |
Completed |
2 |
258 Horseshoe Drive Project |
Completed Project to demolish the house at 258 Horseshoe Drive. Work completed by the Contractor on surveying asbestos and lead inside the home. Underground storage tank removed. |
3 |
Caln Park West Bioswale Project |
Completed Design and specifications have been completed. The project went out to bid on 3/14/2022. Bid approved by BoC. Notice of award sent to contractor. Project start May 2, 2022 with completion by September 9, 2022. |
4 |
Lloyd Avenue Signals Project |
Completed |
5 |
Reed Street Stormwater Project |
Easement talks underway with property owners. Additional survey of the project area is underway. Presentation of proposed project scope to the Board of Commissioners to occur in May 2022. |
6 |
Spackman Farm Driveway Paving |
Completed Project to repave existing driveway and parking area for Spackman Farm will be included as an item in 2022 Road Paving Project. |