Storm Ida Projects
-
Other Projects
<
>
Page under construction - last updated 4/13/2022
The following is a list of Caln Township infrastructure projects intended to address damage caused or exacerbated by Storm Ida. Some of the projects are eligible for partial reimbursement by FEMA and the Township is working diligently to follow all FEMA regulations in order to maximize our reimbursements. In order to be eligible for partial FEMA reimbursement, projects must be completed within 18 months of the federal disaster declaration (by March 2023, in our case). As we work through the engineering and bid process for these projects, status updates will be provided.
# |
Project Title |
Status |
1a |
Municipal Drive Bridge Replacement |
Survey has been completed and data to be accepted by 3/25/2022. Geotech fieldwork has been completed and the Geotech report was completed by 3/14/2022. Currently developing an informational submission with costs and alternatives analysis for the 1st Commissioners' meeting in April. The intent is to complete the General Permit-11 for submission to PADEP by the end of April 2022. |
1b |
Municipal Drive Streambank and Pedestrian Walkway Repair |
Bids received / project awarded. Construction ongoing as of April 11 |
2 |
Moore Road Bridge Replacement |
Survey has been completed and data accepted on 3/21/2022. The intent is to complete the General Permit-11 for submission to PADEP and complete the final design by the end of April 2022. |
3 |
Barley Sheaf Road Swale |
Survey has been completed. Currently developing plot plans in AutoCAD with the intent of beginning the design in April 2022. |
4 |
East Fisherville Road Bridge Demolition* |
The bid manual is complete. The project will be presented at the April 24th Board of Commissioners meeting for final approval to go out to bid. The PADEP will issue an approval letter shortly. |
5 |
Fisherville Road Streambank Stabilization (and road repair) |
Work started April 11. Expect projection by end of April 2022. After project completion, PADEP requires that a General Permit application be submitted to confirm the emergency permit scope of work for their records. |
6 |
G.O. Carlson (Beaver Creek Crossing)* |
Survey has been completed. A preliminary analysis has been completed. Developing emergency permit for submission to PADEP. The emergency permit will allow the Township to clean the stream and culverts of debris to elminate flooding risk in the short-term. The intent is to obtain an emergency permit and perform the cleaning as well as start the design in April 2022. |
7 |
Humpton, Lynn, Williams Culvert Repair* |
Survey has been completed. Currently developing plot plans in AutoCAD with the intent of beginning the design in April 2022. |
8 |
N. Bailey Road Inlet and Culvert Repair |
Survey has been completed. Currently developing plot plans in AutoCAD with the intent of beginning the design in April 2022. |
9 |
N. Barley Sheaf Road Culvert |
Survey has been completed. Currently developing plot plans in AutoCAD with the intent of beginning the design in April 2022. |
10 |
Park Drive Culvert Repair* |
Survey has been completed. Preliminary analysis and design have been completed. The intent is to have the final project design at 90% completion by the of April 2022. |
11 |
S. Lloyd Ave. Streambank Stabilization (and culvert repair) |
Survey has been completed and General Permit submitted to PADEP. Final design and specifications to be compete by May 2022. Anticipate receipt of approved General Permit from PADEP by May 2022. Expect to bid June 2022 and intend construction to begin in August 2022 with anticipated project completion in November 2022. |
*Project is not eligible for FEMA reimbursement |
# |
Project |
Status |
1 |
2022 Road Paving Project |
The bid manual is under final review and will be presented to the Board of Commissioners at their April 14th meeting, along with the street list and cost estimates for approval. |
2 |
258 Horseshoe Drive Project |
Project to demolish the house at 258 Horseshoe Drive. Work completed by the Contractor on surveying asbestos and lead inside the home. Removal of underground storage tank scheduled for April 4, 2022. |
3 |
Caln Park West Bioswale Project |
Design and specifications have been completed. The project went out to bid on 3/14/2022. Bidding ends 4/4/2022. Award 4/14/2022 and intend construction to being early May 2022. |
4 |
Lloyd Avenue Signals Project |
Higgins Electric (awarded contractor) is waiting on new signal poles. Upon delivery, Higgins Electric will start the project in earnest. |
5 |
Reed Street Stormwater Project |
Additional survey of the project area is underway. Presentation of proposed project scope to the Board of Commissioners to occur in May 2022. |
6 |
Spackman Farm Driveway Paving |
Project to repave existing driveway and parking area for Spackman Farm will be included as an item in 2022 Road Paving Project. |