Storm Ida Projects
-
Other Projects
<
>
Check back for updates - last updated February 15, 2023
The following is a list of Caln Township infrastructure projects intended to address damage caused or exacerbated by Storm Ida. Some of the projects are eligible for partial reimbursement by FEMA and the Township is working diligently to follow all FEMA regulations in order to maximize our reimbursements. As we work through the engineering and bid process for these projects, status updates will be provided. Where applicable, click on a project name to access a PDF of the engineer's design file for that project.
# |
Project Title |
Status |
1a |
Bridge arch shop drawings in progress. Working with PECO on relocation of poles and wires - demolition to begin once PECO work complete. Notice to proceed sent January 18, 2023 - anticipated completion by 7/17/2023. Preconstruction meeting January 20th. Out for bids on November 23rd, bids due December 14th, bid announcement at December 22nd meeting of the Board. Design completed and bid documents prepared. Survey has been completed and data to be accepted by 3/25/2022. Geotech fieldwork has been completed and the Geotech report was completed by 3/14/2022. Project design underway. The intent is to complete the General Permit-11 for submission to PADEP and complete the final design by mid-may 2022. |
|
1b |
Municipal Drive Streambank and Pedestrian Walkway Repair |
Completed |
2 |
Working with PECO on relocation of poles and wires and gas main. On schedule. Notice to proceed sent January 18, 2023 - anticipated completion by 6/7/2023. Preconstruction meeting January 24th. Out for bids on November 23rd, bids due December 14th, bid announcement at December 22nd meeting of the Board. Design completed and bid documents prepared. Survey has been completed and data accepted on 3/21/2022. The intent is to complete the General Permit-11 for submission to PADEP and complete the final design by mid-May 2022. |
|
3 |
Tree work started - on schedule. Project construction underway - anticipated completion by 4/6/2023. Bid awarded and project anticipated to begin within next 60 days (from 11/21), subject to weather and supply chain issues. Notice to affected residents will be issued prior to work starting. Survey has been completed. Currently developing plot plans in AutoCAD with design underway. |
|
4 |
East Fisherville Road Bridge Demolition* |
Completed Project out to bid on PennBID with due date of April 21, 2022 with bid award on April 28, 2022. The PADEP will issue an approval letter shortly. |
5 |
Fisherville Road Streambank Stabilization (and road repair) |
Completed |
6 |
G.O. Carlson (Beaver Creek Crossing)* |
Survey has been completed. A preliminary analysis has been completed. Developing emergency permit for submission to PADEP. The emergency permit will allow the Township to clean the stream and culverts of debris to elminate flooding risk in the short-term. The intent is to obtain an emergency permit and perform the cleaning in April 2022/early May 2022. Design underway. |
7 |
Humpton, Lynn, Williams Culvert Repair* |
Survey has been completed. Currently developing plot plans in AutoCAD with design underway. |
8 |
In progress - on schedule. Mobilized 1/20/2023 - anticipated completion by 3/1/2023. Notice to proceed sent 11/1/2022. Bid awarded and project anticipated to begin within next 60 days (from 11/21), subject to weather and supply chain issues. Notice to affected residents will be issued prior to work starting. Survey has been completed. Currently developing plot plans in AutoCAD with design underway. |
|
9 |
Tree work started - on schedule. Notice to proceed sent 12/8/2022 - anticipated completion by 4/6/2023. Notice to affected residents will be issued prior to work starting. Survey has been completed. Currently developing plot plans in AutoCAD with design underway. |
|
10 |
Awaiting material that has been ordered. Notice to proceed sent 1/12/2023 - anticipated completion by 5/12/2023. Out to bid. Survey has been completed. Preliminary analysis and design have been completed. The intent is to have the final project design at 90% completion by the of April 2022. |
|
11 |
S. Lloyd Ave. Streambank Stabilization (and culvert repair) |
On schedule - not yet mobilized. Notice to proceed sent 12/8/2022 - anticipated completion by 3/22/2023. Bid awarded and project anticipated to begin within next 60 days (from 11/21), subject to weather and supply chain issues. Notice to affected residents will be issued prior to work starting. Survey has been completed and General Permit submitted to PADEP. Final design and specifications to be compete by May 2022. Anticipate receipt of approved General Permit from PADEP by May 2022. Expect to bid June 2022 and intend construction to begin in August 2022 with anticipated project completion in November 2022. |
*Project is not eligible for FEMA reimbursement |
# |
Project |
Status |
1 |
2022 Road Paving Project |
Completed |
2 |
258 Horseshoe Drive Project |
Completed Project to demolish the house at 258 Horseshoe Drive. Work completed by the Contractor on surveying asbestos and lead inside the home. Underground storage tank removed. |
3 |
Caln Park West Bioswale Project |
Completed Design and specifications have been completed. The project went out to bid on 3/14/2022. Bid approved by BoC. Notice of award sent to contractor. Project start May 2, 2022 with completion by September 9, 2022. |
4 |
Lloyd Avenue Signals Project |
Completed |
5 |
Reed Street Stormwater Project |
Easement talks underway with property owners. Additional survey of the project area is underway. Presentation of proposed project scope to the Board of Commissioners to occur in May 2022. |
6 |
Spackman Farm Driveway Paving |
Completed Project to repave existing driveway and parking area for Spackman Farm will be included as an item in 2022 Road Paving Project. |