-
Storm Ida Projects
-
Other Projects
<
>
Check back for updates - last updated February 7, 2024
The following is a list of Caln Township infrastructure projects intended to address damage caused or exacerbated by Storm Ida. Some of the projects are eligible for partial reimbursement by FEMA and the Township is working diligently to follow all FEMA regulations in order to maximize our reimbursements. As we work through the engineering and bid process for these projects, status updates will be provided. Where applicable, click on a project name to access a PDF of the engineer's design file for that project.
# |
Project Title |
Status |
1a |
Completed! |
|
1b |
Municipal Drive Streambank and Pedestrian Walkway Repair |
Completed |
2 |
Completed |
|
3 |
Completed |
|
4 |
East Fisherville Road Bridge Demolition* |
Completed |
5 |
Fisherville Road Streambank Stabilization (and road repair) |
Completed |
6 |
G.O. Carlson (Beaver Creek Crossing)* |
Working with DEP on permit and grant opportunities to include stream bank stabilization for expanded work needed. Project scope expanded to include streambank stabilization. |
7 |
Humpton, Lynn, Williams Culvert Repair* |
Working with DEP on permit and grant opportunities to include stream bank stabilization for expanded work needed. Project scope expanded to include streambank stabilization. |
8 |
Completed |
|
9 |
Completed |
|
10 |
Completed |
|
11 |
S. Lloyd Ave. Streambank Stabilization (and culvert repair) |
Completed |
*Project is not eligible for FEMA reimbursement |
# |
Project |
Status |
1 |
2022 Road Paving Project |
Completed |
2 |
258 Horseshoe Drive Project |
Completed Project to demolish the house at 258 Horseshoe Drive. Work completed by the Contractor on surveying asbestos and lead inside the home. Underground storage tank removed. |
3 |
Caln Park West Bioswale Project |
Completed Design and specifications have been completed. The project went out to bid on 3/14/2022. Bid approved by BoC. Notice of award sent to contractor. Project start May 2, 2022 with completion by September 9, 2022. |
4 |
Lloyd Avenue Signals Project |
Completed |
5 |
Reed Street Stormwater Project |
Bulk of project completed, final paving and finalization of work in Spring 2024 |
6 |
Spackman Farm Driveway Paving |
Completed Project to repave existing driveway and parking area for Spackman Farm will be included as an item in 2022 Road Paving Project. |