610-384-0600
Caln Township
  • Services
    • Pay My Bills
    • Trash & Recycling
    • Chipping & Yard Waste
    • Pavilion Rental
    • Parks >
      • Beaver Creek Trail
      • Caln Meadow Park
  • RESOURCES
    • News
    • Permits & Applications
    • Questions & Requests
    • Upcoming Developments
    • Infrastructure Projects
    • Events >
      • Summer Series
      • National Night Out
      • Community Day >
        • Art Show
      • Art in the Park
      • Clean Up Crew
    • Maps
    • History
    • Community Links
    • Stormwater
    • New Residents
    • Jobs
  • Government
    • Township Code
    • Board of Commissioners
    • Boards & Commissions >
      • Planning Commission
      • Zoning Board
      • Historical Commission
      • Parks & Rec Board
      • Civil Service Commission
      • Municipal Authority
      • Environmental Advisory Council
      • Volunteer
    • 2017 Comprehensive Plan
  • Departments
    • Administration
    • Building & Life Safety >
      • Community Program Requests
      • Fire Services
      • Fire Marshal
      • Ambulance Services
    • Finance
    • Ingleside Golf Club
    • Police >
      • Police Services
      • Patrols & Units
      • Protect Yourself
      • FAQs & Tips
      • Solicitation License
      • Prescription Drug Drop-Off
      • Police Blotter
      • Security Camera Registration
      • No Solicitation Registry
    • Public Works
    • Trash & Sewer
  • Fee Schedule
  • Minutes & Agendas
    • Meeting Recordings
  • Sustainability
  • Services
    • Pay My Bills
    • Trash & Recycling
    • Chipping & Yard Waste
    • Pavilion Rental
    • Parks >
      • Beaver Creek Trail
      • Caln Meadow Park
  • RESOURCES
    • News
    • Permits & Applications
    • Questions & Requests
    • Upcoming Developments
    • Infrastructure Projects
    • Events >
      • Summer Series
      • National Night Out
      • Community Day >
        • Art Show
      • Art in the Park
      • Clean Up Crew
    • Maps
    • History
    • Community Links
    • Stormwater
    • New Residents
    • Jobs
  • Government
    • Township Code
    • Board of Commissioners
    • Boards & Commissions >
      • Planning Commission
      • Zoning Board
      • Historical Commission
      • Parks & Rec Board
      • Civil Service Commission
      • Municipal Authority
      • Environmental Advisory Council
      • Volunteer
    • 2017 Comprehensive Plan
  • Departments
    • Administration
    • Building & Life Safety >
      • Community Program Requests
      • Fire Services
      • Fire Marshal
      • Ambulance Services
    • Finance
    • Ingleside Golf Club
    • Police >
      • Police Services
      • Patrols & Units
      • Protect Yourself
      • FAQs & Tips
      • Solicitation License
      • Prescription Drug Drop-Off
      • Police Blotter
      • Security Camera Registration
      • No Solicitation Registry
    • Public Works
    • Trash & Sewer
  • Fee Schedule
  • Minutes & Agendas
    • Meeting Recordings
  • Sustainability

Municipal Authority Meeting Minutes, December 18, 2023

12/18/2023

 
                                                         Caln Township Municipal Authority
                                                                   253 Municipal Drive
                                                                 Thorndale, PA 19372
                                                           Monday December 18, 2023
                                                                           7:00 PM
 
Those Present and Absent:
George Chambers – Chairperson (Absent)                                                         
Paul Mullin – Vice Chairperson
William A. Schew – Treasurer
Tony DiSario – Assistant Treasurer/Assistant Secretary  
Noel Bernard – Secretary
Scot Gill – Wastewater Department Director
Jennylyn Tanedo – Recording Secretary
Ross Bickhart – Gilmore & Associates, CTMA Engineer
Vince Pompo- LambMcErlane, CTMA Solicitor (Absent)
 
Call to Order
The meeting of the Caln Township Municipal Authority was called to order by Mr. Mullin at 7:00 p.m. The meeting was held in person at the Caln Township Municipal Building Meeting Room located at 253 Municipal Drive Thorndale, Pa and via Zoom. The regular scheduled meeting of the Caln Township Municipal Authority was advertised in the Daily Local News on December 27, 2023, and the agenda was posted on the Caln Township Website and Lobby on December 15, 2023. Copies of the Agenda were made available to the public.
 
Minutes of the November 20, 2023, Meeting
Mr. Mullin called for additions or corrections to the November minutes. There were none. After discussion, Mrs. Bernard motioned, seconded by Mr. Schew, to adopt the November 2023 minutes, as presented. The vote passed 4.0.
 
Public Comment                         
Mr. Mullin called for public comments. There were none.
 
Act 537 Plan/ Additional Capacity Update/ Dara Update
Mr. Gill presented to the Board a spreadsheet showing the status of pending projects that will be needing capacity in the future, the 52-week average chart, Dara weekly flow report. Mr. Gill informed the Board that he spoked with Mr. Mays and discussed why they are moving away from the idea of using the Membrane System for the expansion and he stated that Mays said that some of their concerns are that with a more advanced controls and electrical system and how their operators will be able to adjust, very difficult to clean, very limited when it comes to flood control, and if they decided to go the route of Membrane System and things didn’t work out with it, they could never go back to a conventional system without replacing tanks. Mr. Gill added that according to Mr. Mays the Membrane System is designed mostly for smaller systems and has very little use on the larger plants in the US.
 
I/I Reduction Program
Mr. Gill informed the Board that the Caln Interceptor Phase 5 CAL-01-22 with Standard Pipe Services, LLC (Insitufrom Technologies) has been completed and the Gilmore is currently working on finalizing punch list items, payment requests and project closeout.   Mr. Gill presented to the Board the 1st payment request from Standard Pipe Services, LLC (Insitufrom Technologies) for Contract# CAL-01-22 in the amount of $35,160.30. After discussion, Mr. DiSario made a motion, seconded by Mrs. Bernard, to recommend to the Board of Commissioners to authorize the release of Standard Pipe Services, LLC. (Insituform Technologies). 1st Payment request for Contract # CAL-01-22 in the amount of $35,160.30 contingent that all work is completed to the satisfaction of the authority engineer. The vote passed 4.0.
 
Mr. Gill presented to the Board the Award Recommendation letter and the Bid Tabulation from Gilmore for the 2024 Grouting Project CAL-01-23. Mr. Bickhart recommended that the contract be awarded to Sewer Specialty Services Company, Inc. in the amount of $141,622.50 for the base bid. After discussion, Mr. Schew made a motion, seconded by Mr. DiSario, to award the 2024 Grouting Project CAL-01-23 to Sewer Specialty Services Company Inc. in the amount of $141,622.50 for the base bid and to authorize the CTMA Chairperson to sign all required documents pertaining to the contract once the signed contract is received back from the contractor, reviewed, and approved by the CTMA’s Solicitor and Engineer. The vote passed 4.0.
 
Willows at Valley Run Project Update
Mr. Gill informed the Board that on June 22, 2022, the Authority entered into a Sewer Construction Financial Security Agreement and Performance Bond with Willows at Valley Run, LLC Phase 1 who agreed to post a Performance Bond in the sum of $127,739.37 representing 110% of the cost of the Phase 1 Sewer Improvements as set forth in the Agreement. The Agreement states that the developer may request a reduction of the Performance Bond, as the developers completes various segments of the sewer improvements, and the design engineer of the sewer improvements certifies to the Authority engineer that the sewer improvements have been completed in accordance with the Plan. Mr. Gill added that the developer agrees to allow the conversion of the Performance Bond to maintenance security in the amount of fifteen percent (15%) of the cost of the Off-Site Sewer Improvements to be offered for dedication to the Authority. Mr. Gill presented to the Board the Willows at Valley Run Performance Bond No.30151172 Certificate of Partial Completion that would need to be signed by the Chairperson. After discussion, Mr. DiSario made a motion, seconded by Mrs. Bernard to authorize the Chairperson to sign the enclosed Certificate of Partial Completion for the Phase 1 Bond Reduction in the form as presented and authorize the reduction of Sanitary Sewer Phase 1 Performance Bond by $123,154.25. The vote passed 4.0.
 
Mr. Gill Informed the Board that April 12, 2023, the Authority entered into a Sewer Construction Financial Security Agreement and Performance Bond with the Willows at Valley Run, LLC. Phase 2 who agreed to post a Performance Bond in the sum of $85,121.36 representing 110% of the cost of Phase 2 Sewer Improvements as set forth in the Agreement. The agreement states that the developer may request a reduction of the Performance Bond, as the developer completes various segments of the sewer improvements, and the design engineer of the sewer improvements certifies to the Authority engineer that the sewer improvements have been completed in accordance with the Plan. Mr. Gill presented to the Board the Willows at Valley Run Performance Bond No.30151178 Certificate of Completion that would need to be signed by the Chairperson. After discussion, Mr. Schew made a motion, seconded by Mrs. Bernard to authorize the Chairperson to sign the enclosed Certificate of Completion for the Phase 2 Bond Reduction in the form as presented and authorize the reduction of the Sanitary Sewer Phase 2 Performance Bond by $85,121.36. The vote passed 4.0.
 
2024 Professional Consultants Rate Schedule
Mr. Gill presented to the Board Resolution 2023-4-CTMA, adopting the 2024 schedule of fees for the Authority’s Professional Consultants. After discussion, Mr. Schew made a motion, seconded by Mr. DiSario, to adopt Resolution 2023-4-CTMA adopting the 2024 schedule of fees for the Authority’s Professional Consultants. The vote passed 4.0.
 
Mr. Gill recommended to the Board extend the Caln Township Municipal Authority’s General Engineering Consulting Agreement, dated December 16, 2013, with Gilmore & Associates, Inc. until December 31, 2024. After discussion, Mr. Schew made a motion, seconded by Mrs. Bernard to extend the Caln Township Municipal Authority’s General Engineering Consulting Agreement, dated December 16, 2013, with Gilmore & Associates, Inc. until December 31, 2024. The vote passed 4.0.
 
Mr. Gill recommended to the Board to retain Hydraterra Professionals, LLC. for special projects at their proposed 2024 rate schedule and to extend Caln Township Municipal Authority’s General Engineering Consulting Agreement with Hydraterra Professionals, LLC. Until December 31, 2024. After discussion, Mr. DiSario made a motion, seconded by Mr. Schew, to retain Hydraterra Professionals, LLC.  For special projects at their proposed 2024 rate schedule and to extend Caln Township Municipal Authority’s General Engineering Consulting Agreement until December 31, 2024. The vote passed 4.0.
 
Financials; Sewer Fund,
Mr. Gill reviewed the sewer financial summary and the revenues and expenditures for the Sewer Operating Fund for the month of November 2023 and the balances in Act 57 and Sewer Capital Funds. After discussion, Mr. DiSario made a motion, seconded by Mr. Schew, to accept the November financials, as submitted.  The vote passed 4.0.
 
Penalty Waiver Request Update
Mr. Gill presented to the Board the 2023 summary of penalty waiver request from the finance department. Mr. Gill informed the Board that no penalty waiver requests were made for the month of November.
 
2024 Draft Rate Resolution
Mr. Gill presented Resolution 2023-5-CTMA establishing the sewer rates effective January 1, 2024, and approving the 2024 Operating, Act 57 and Capital Fund budgets. The resolution proposes an increase in sewer rates. Mr. DiSario made a motion, seconded by Mrs. Bernard adopting Resolution # 2023-5-CTMA effective January 1, 2024. The vote passed 4.0.
 
Director’s Report
Mr. Gill discussed his Director’s Report and noted a list of current projects which the Department is working on and their progress.
 
Adjournment
There being no further business, Mr. DiSario made a motion, seconded by Mrs. Bernard, to adjourn the December 18,2023, meeting at 8:05 pm. The vote passed 4.0.


Respectfully Submitted

 
     Jennylyn Tanedo,
     Recording Secretary
12.18.2023_ctma_minutes.pdf
File Size: 773 kb
File Type: pdf
Download File


Comments are closed.

    MINUTES

    Read through past minutes from the Municipal Authority meetings. You may also download a pdf file for each meeting.

    ​Agendas for future meetings can be found here. 

    Archives

    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    January 2022
    December 2021
    November 2021
    October 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    December 2018
    November 2018
    October 2018
    August 2018
    July 2018
    June 2018
    April 2018
    March 2018
    January 2018
    October 2017
    September 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    January 2017
    December 2016
    October 2016
    September 2016
    August 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    December 2014
    December 2013

610-384-0600
​[email protected]

HOURS: Mon-Fri 8AM-4:30PM


Staff Login - New


Picture
253 Municipal Dr, Thorndale, PA 19372
​(C) 2025 Caln Township