Caln Township Municipal Authority
253 Municipal Drive
Thorndale, PA 19372
Monday September 28, 2026
7:00 PM
Those Present and Absent:
George Chambers – Chairperson
Paul Mullin – Vice Chairperson
William A. Schew – Treasurer (Absent)
Tony DiSario – Assistant Treasurer/Assistant Secretary
Noel Bernard – Secretary
Scot Gill – Wastewater Department Director
Don Vymazal – Township Manager
Jennylyn Tanedo – Recording Secretary
Ross Bickhart – Pennoni Associates, CTMA Engineer
Vince Pompo- LambMcErlane, CTMA Solicitor (Absent)
Call to Order
The meeting of the Caln Township Municipal Authority was called to order by Mr. Chambers at 7:00 p.m. The meeting was held in person at the Caln Township Municipal Building Meeting Room located at 253 Municipal Drive Thorndale, Pa. The meeting of the Caln Township Municipal Authority was advertised in the Daily Local News on December 22, 2025, and the agenda was posted on the Caln Township Website and Lobby on September 25, 2026. Copies of the Agenda were made available to the public.
Minutes of August 24, 2026, Meeting
Mr. Chambers called for additions and corrections for the July Minutes. There were none. After discussion, Mr. Mullin made a motion, seconded by Mr. DiSario, to adopt August 24, 2026, Minutes as presented. The vote passed 3-0-1 with Ms. Bernard abstaining.
Public Comment
Mr. Chambers called for public comments. There were none.
Act 537 Plan/ Additional Capacity Update
Mr. Gill presented to the Board a spreadsheet showing the status of pending projects that will be needing capacity in the future, the 52-week average chart, Dara weekly flow report and DARA Tributary Area Total Adjusted Flows Hydraulic Loadings Charts. Mr. Chambers updated the Board on the status of Dara plant upgrades and expansion. He mentioned that Dara received approval for the limited fire sprinkler and alarm requirements from East Caln Township.
I/I Reduction Program
Mr. Gill updated the Board on the 2026 Grouting Project and informed the Board that Sewer Specialty Co. Inc completed the 2026 Grouting Project on September 2nd, 2026. Mr. Gill then presented to the Board payment request #2 from Sewer Specialty Co Inc. in the amount of $95,919.97. After discussion, Ms. Bernard made a motion, seconded by Mr. DiSario, to recommend to the Board of Commissioners to authorize release of the payment, contingent that all work is completed to the satisfaction of the authority engineer and the contractor provides the certified payrolls for the work period associated with the application for payment. The vote passed 4-0.
Mr. Gill informed the Board that the 2027 Grouting Project will involve the cleaning and televising, testing of all pipe joints, grouting joints that fail the test, performing point repairs and grouting manholes on approximately 3,300 linear feet of 8” diameter gravity sewer located in the park and Meadow Drive Area. Additionally, the project includes the installation of approximately 1,434 linear feet of 8” diameter cured in place liner in the Wedgewood Area. Mr. Gill presented the project map and an estimated cost of $322,645. After discussion, Mr. Mullin made a motion, seconded by Ms. Bernard to authorize Pennoni to obtain COSTARS pricing from the Sewer Specialty Services Co Inc. and authorize staff to put together the Contractors Service Agreement between the CTMA and Sewer Specialty Services Co. Inc. for the 2027 Grouting Project which will be presented to the Board at a future meeting for consideration. The vote passed 4-0.
Kings Grant PS Electric Upgrade
Mr. Gill updated the Board on the Kings Grant Pump Station Electric Upgrade Project and informed the Board that as discussed at the May 18th meeting, the Board elected to eliminate the 2-bid alternatives which are rebuilding pumps 1 & 2 and supplying and installing a renewed grinder to make the bid a strictly all electric project to hopefully eliminate any confusion and potentially open it up to more bidders. As part of the project, staff is recommending we still rebuild Pumps 1 and 2 and install a renewed grinder. The department will work with a contractor to complete this work separately from the electric upgrade project. Mr. Gill presented to the Board a quote in the amount of $18,355.16 for the renewed grinder for their review. After discussion, Mr. DiSario made a motion, seconded by Ms. Bernard to authorize staff to proceed with the purchase from JWC Environmental a replacement grinder system in the total amount of $18, 355.16 utilizing the Costars Program and authorize the Chairman to sign the quote as presented. The vote passed 4-0.
Raye Road Phase 2 Project
Mr. Gill updated the Board on the Raye Road Phase 2 Project. Mr. Gill informed the Board that the contractor has sent in their required paperwork, and the contract has been signed. Mr. Gill also stated that Pennoni is in the process of setting up the preconstruction meeting and the contractor is still working on assembling and submitting their material submittals.
North Caln Road PS Abandonment Project
Mr. Gill presented to the Board an estimate from Pennoni for the North Caln Road Pump Station Abandonment Project that will be bid in early 2027. Mr. Gill added that this is an estimated cost ($20,000) which will be billed time and material for Pennoni to conduct site visits, supplemental topographic survey and prepare drawings and specifications to a bid ready state and prepare cost estimates to be presented to the Authority in early 2027 for consideration to go out to bid. After discussion, Mr. Mullin made a motion, seconded by Ms. Bernard, to authorize staff and Authority engineers to proceed with preparing the drawings, specifications and cost estimate for the North Caln Road Pump Station Abandonment Project. The vote passed 4-0.
Municipal Drive PS Subsidence Repair Project
Mr. Gill updated the Board on the Municipal Drive Pump Station Subsidence Repair. Mr. Gill stated that On September 4, 2026, after the heavy rain we have been having, the department found a subsidence that started to form along the western side of the Municipal Pump Station. Mr. Gill stated that he immediately reached out to Mr. Bickhart that day and he engaged their Geotechnical department to stop out and look at it to find out the extent of the subsidence since it’s so close to the foundation of the building. Mr. Gill then stated that on September 16th we excavated the area with the assistance of the Public Works Department along with Pennoni’s geotechnical department and found a large void beneath the pavement, on the order of 3 feet deep and the void extended underneath the pump station control building by approximately 5 feet. Mr. Bickhart then engaged his geotechnical department to conduct ground penetrating radar investigation into the entire pump station site which was completed on September 21st so that they can see if there are any additional voids that may exist below grade. Mr. Gill added that Pennoni’s geotechnical department will then analyze the findings from the September 16th investigation along with the findings of the ground penetrating radar and develop a recommended repair strategy. At this time, it is anticipated that would likely consist of grout injections to seal off the sinkhole openings, and then flowable fill to fill in the larger void areas at an estimated cost of $70,000. Mr. Gill added that there is a good chance the repairs will be made between the September and October Board meetings. After discussion, Ms. Bernard made a motion, seconded by Mr. Mullin to authorize staff and Authority engineer to proceed with the emergency sinkhole repair at the Municipal Drive Pump Station in accordance with Section 5614 Paragraph D of the Municipality Authorities Act at an estimate cost of $70,000, unless otherwise approved by the Board and to authorize the Board Chairperson to sign the Contractors Services Agreement in the form as presented once the contractor is selected and approved by the Authority’s Solicitor and Engineer. The vote passed 4-0.
2027 CTMA Meeting Dates
Mr. Gill presented to the Board a list of proposed 2027 Municipal Authority meeting dates. After discussion, the Board agreed to table it until the October 26, 2026, Meeting to give the Board a chance to review.
Financials; Sewer Fund,
Mr. Gill reviewed the sewer financial summary and revenues and expenditure for the Sewer Operating Fund for the month of August 2026 and the balances in Act 57 and Sewer Capital Funds. After discussion, Mr. DiSario made a motion, seconded by Ms. Bernard, to accept the August financials, as submitted. The vote passed 4-0.
Delinquent Collection Update
Mr. Gill presented to the Board a memo from the finance department that gives an update on the status of the prior year’s delinquent collections.
Penalty Waiver Request Update
Mr. Gill presented to the Board the August 2026 penalty waiver request spreadsheet which stated there is one request for the month of August 2026.
Director’s Report
Mr. Gill discussed his August Director’s Report and noted a list of current projects which the Department is working on and their progress.
Adjournment
There being no further business, Mr. DiSario made a motion, seconded by Mr. Mullin, to adjourn the September 28,2026 meeting at 8:15 pm. The vote passed 4-0.
Respectfully Submitted
Jennylyn Tanedo,
Recording Secretary